
|
REKINDLING THE FIRES The Story of the Appalachian Blacksmiths Association By Paul Lacy Part six: The Cedar Lakes Shop Power Hammer The 50 Lb. Little Giant power hammer at
Cedar Lakes was put into operation prior to Jim Wallace’s workshop in
1980. The workshop participants produced the entrance hall table that now
stands in the Cedar Lakes cafeteria lobby. John Cornish and I were thrilled to see
that Tim Pyles (Cedar Lakes Craft Coordinator) had arranged for the
hammer's purchase in 1979 along with the principal contents of an entire
blacksmith shop. The forging equipment owned by Cedar Lakes was minimal
until that time. John and I had attended Francis Whitaker's workshop at
Cedar Lakes during the summer of 1979 and we were thrilled to see the
Little Giant there, laying on it's side, in all of its grease and
soot-dripping glory. We promptly appointed ourselves its
guardians and, following the workshop, set about the task of cleaning
(transferring the dirt from the hammer to us) and disassembling the badly
rusted and broken foot pedal assembly. I took the pivot home and made a
new one on the lathe. The
next time we got together, John and I forged a new treadle band—the
original was to far gone to save. We had a windfall the preceding summer in
the form of a U.S. Army Corps. of Engineers encampment a Cedar Lakes in
search of worthy projects. They provided the labor to cut through the
relatively thin concrete of the Cedar Lakes shop floor and then excavated a
hole for approximately one cubic yard of concrete to be poured as a flush
foundation. Appropriate mounting bolts were set in the concrete pour and
the hammer was secured. A piece of rubber conveyor belting between the
base and the foundation serves as a cushion. We were delighted to find the hammer in
this upright and bolted-down condition when, as a group of volunteers, a
half-dozen ABA members met as a three-day advance party prior to the Jim
Wallace workshop. We knew that Jim Wallace’s workshop would
be "Big" and that a special group project was to take place,
which would utilize the new hammer to construct the elements of the
project. The volunteer party was also charged with a
diverse set of tasks that involved making and setting up extra forge
stations, mounting anvils and post vises and constructing tool tables,
mounting boards, and a welding station, and generally fine tuning what had
previously been a VoAg welding building into a blacksmith shop. Tim Pyles
had decided the blacksmith craft was a "GO" for the Cedar Lakes
Craft Center program and had the maintenance staff install the hoods from
the old dining hall in the building as smoke catchers. Tim had also followed the shopping list I
had given him to the letter; he had obtained the necessary steel to hang a
small line shaft and the new single phase motor, and of course the
necessary pulleys, belts and bearings, along with appropriate switch gear
for the Little Giant’s motor. Glenn Horr assisted me ably in hanging the
steel, it having been decided that the existing steel in the shop was
sturdy enough to support the drive. The hammer was a center clutch model
and was intended for overhead drive. Because the clutch bearing was just
starting to get a trifle loose, all involved agreed that the overhead
drive would provide the least damaging side load on the bearings. I had just purchased a portable DC welder
the previous year, which greatly facilitated the out of position arc
welding we had to do to fabricate the drive. Since the work of driving the hammer was
performed without drawings, a small XY table was used to put keyways in
the driveshaft at the right place with an end mill. We used the drill
press in the Cedar Lakes woodshop. Glenn and I accomplished this, using the
old Jim Wallace adage, " It is usually easier to beg forgiveness than
to seek permission." At some point, we decided that a more fair
appropriation of assets would be for one of the two woodshop drill presses
to be located permanently within the blacksmith shop. Since we had sullied
one of the presses with metal shavings, that one became the donor drill
press. Throughout the bulk of the pre-workshop
session following Jim's arrival, he assumed the role of Chief Pusher and
Whip Cracker and opined that if we didn't get a move on, the workshop
would be upon us, with the hammer not running and disaster would follow. This being 1980, I had not had the benefit
of watching American Chopper, or American Hotrod, to get a mindset for the
deadline thing and as for metal working being fun. But I'm happy to report
that when the hammer was needed, it was started without problems and
performed the tasks asked of it throughout the week. I recall in addition to the previously
mentioned, that Boyd Holtan, Pete Minier, Terry Arlett, Jay Hurley, and
Frank Bordo all contributed to the pre-workshop fixup. I have probably run
the risk of creating a life enemy by omitting someone, but these are the
names of those that were of greatest personal help to me at that event. I
could claim omission due to senility, this being the year that I
officially enter old fartdom, but I'm sure Boyd will clear up the record
and you can save my face by editing away the errors in this last
paragraph. Thanks, Paul Lacy Editor’s
note: Boyd
Holtan wrote “The ABA members who contributed to the work session were:
Frank Bordo, Robert Dennis, Boyd Holtan, Glenn Horr, Jay Hurley, Paul
Lacy, Pete Minier, George Nichols, Bob Selvaggio, Ed Small, and John
Schlessinger.” in part three of “Rekindling the Fires”.
|